Project for the Web: format grid and viewing custom fields/columns in grid in Power BI...

Hi Team

I'm using Project for the Web (PfW).  Can anyone help me with the following two problems:

  • I want to colour certain rows in the grid view but can't seem to do it.  Am I missing something?  Even if selecting 'label your task' colour and it showed in the grid view, that would be OK.
  • I created some custom fields/columns in the grid view but they don't appear in the Power BI report.  I'm using the default PfW PBI template in Github.  Again, am I missing something?

Many thanks 

James

4 Replies

    • GreemaPande's avatar
      GreemaPande
      Copper Contributor
      Is there any alternate, how can I show values of the custom columns of Project for Web Task Grid in Power BI report?
    • Jamesp435's avatar
      Jamesp435
      Brass Contributor
      Hi Paul
      I seem to have failed the initiative test. I can't find the best response button.
    • Jamesp435's avatar
      Jamesp435
      Brass Contributor
      Thanks for this Paul. I find it ridiculous that MS doesn't give you access to these custom fields. I'm sure you have better insight but I don't see much real change from what we saw in Prague 3½ years ago. Hey ho.