Forum Discussion
johnsonke01
Aug 03, 2023Copper Contributor
Project for the Web Dependencies Broken
I'm unable to to make dependencies between my project tasks. Under no circumstance am I able to connect any decencies between tasks. Is this a bug that is currently being worked on?
Aug 03, 2023
Johnsonke01 --
Select a block of tasks that you want to link, right-click anywhere in the selected block, and then select the Add Dependency item on the shortcut menu. Does that work for you? I just tested and it does work for me. Let us know and we will try to help you.
Select a block of tasks that you want to link, right-click anywhere in the selected block, and then select the Add Dependency item on the shortcut menu. Does that work for you? I just tested and it does work for me. Let us know and we will try to help you.
johnsonke01
Aug 03, 2023Copper Contributor
Thanks Dale that did work! Something is out of wack tho as i can't make dependencies in the Timeline view, connecting the dots. It shows a connection but then when reloaded it is lost. This should work tho, thank you!
- PearlandGCSRTAug 06, 2023Copper Contributor
johnsonke01 I am having issues too. If I add a dependency from the first pop up it adds FS to the task number, but doesn’t add the actual link. Every time I click it adds another FS to the task.
I tried adding via the task details and have the same issue.
Same issue if I try a different dependency type.
started happening this week!