Forum Discussion
Leigh Wood
Mar 09, 2020Copper Contributor
Project for the Web - weekends
Hi We have recently begun using Project for the Web and frankly, it has been great. It has made a big difference, however, there is one small snag. As an IT company, we often work on a weekend, b...
Apr 30, 2021
Leigh --
You cannot schedule tasks over the weekend using the native "front end" Project for the Web application. However, you can create custom calendars and configure weekend only resources using the "back end" of Project for the Web, which is the Microsoft Dynamics platform. I realize that is probably not an option for most users, and frankly, I believe people should be able to do custom scheduling using the "front end" Project for the Web." Sorry, but hope this helps.
You cannot schedule tasks over the weekend using the native "front end" Project for the Web application. However, you can create custom calendars and configure weekend only resources using the "back end" of Project for the Web, which is the Microsoft Dynamics platform. I realize that is probably not an option for most users, and frankly, I believe people should be able to do custom scheduling using the "front end" Project for the Web." Sorry, but hope this helps.
Michael_Kleinpaste
Apr 30, 2021Copper Contributor
Dale_HowardMVP Thanks for the info. As you already understand that's not an option for most users and huge oversite. Each "tier" of project should have some overlapping functionality. The web version should include weekends and the full project should be able to filter them out if desired.