Project for the Web - there are limitation of custom fields to 10, any way we can have 50 columns

Project for the Web there are limitation of custom fields to 10, if there any way we can have more columns e.g. 50 custom columns and it get's visible for tasks
  • Dale_HowardMVP's avatar
    Feb 12, 2024
    durgeshjhala --

    No, 10 custom fields is a hard limit in Project for the Web. If you truly need 50 custom fields in a project, I would recommend you consider using the Microsoft Project desktop application instead of Project for the Web. Sorry, but hope this helps.