Forum Discussion
durgeshjhala
Feb 12, 2024Copper Contributor
Project for the Web - there are limitation of custom fields to 10, any way we can have 50 columns
Project for the Web there are limitation of custom fields to 10, if there any way we can have more columns e.g. 50 custom columns and it get's visible for tasks
- Feb 12, 2024durgeshjhala --
No, 10 custom fields is a hard limit in Project for the Web. If you truly need 50 custom fields in a project, I would recommend you consider using the Microsoft Project desktop application instead of Project for the Web. Sorry, but hope this helps.
Feb 12, 2024
durgeshjhala --
No, 10 custom fields is a hard limit in Project for the Web. If you truly need 50 custom fields in a project, I would recommend you consider using the Microsoft Project desktop application instead of Project for the Web. Sorry, but hope this helps.
No, 10 custom fields is a hard limit in Project for the Web. If you truly need 50 custom fields in a project, I would recommend you consider using the Microsoft Project desktop application instead of Project for the Web. Sorry, but hope this helps.
durgeshjhala
Feb 13, 2024Copper Contributor
Dale_HowardMVPProject for the Web is based on Power Apps platform, is there any way to extend this project and get multiple custom fields and show on the application.
- Malek Al-ShayebFeb 14, 2024Copper ContributorWhile technically you can add the columns to the task table in Power Platform those columns are not displayed and cannot be used from within P4W schedule !