Forum Discussion
Adil365
May 04, 2022Copper Contributor
Project for the Web - Project Tasks Custom Fields - Power BI Reporting
Hello, We're able to add custom fields to Project Tasks table in the Project for the Web, which is a great feature. However, according to this documentation (https://support.microsoft.com/en-...
Paul_Mather
May 04, 2022MVP
Hello Adil365 ,
Unfortunately these custom fields you create here:
Are not available for reporting, they are only available in the Project for the web interface.
Paul