Project for the web - hide column and move column impact all users
Hello everyone,
When I hide a column in my project in Project for the Web, the other users have also an hiding column. Also, when I switch place a column, it's also impacted the others user in their grid.
Is it possible for each users to have a view ? Other users will have their own view ?
Thanks,
- julianm974 --
Nope, not possible. When you are doing co-authoring of a project, all users who have the project open see the same set of columns, displayed in the same order. There is no way to change this behavior. Hope this helps.
2 Replies
- julianm974 --
Nope, not possible. When you are doing co-authoring of a project, all users who have the project open see the same set of columns, displayed in the same order. There is no way to change this behavior. Hope this helps.- julianm974Copper ContributorIt helps but it's a bit disapointing ... Thank you Dale.