Forum Discussion

sonika755's avatar
sonika755
Copper Contributor
Mar 25, 2022
Solved

Project for the Web - Allow Team members to edit/view only his task

Hello,   Project for the web - I created a project and create a security group for projects. added the team members.   Assign the task to teams. Now only task owner should able to edit the percen...
  • RodFromm's avatar
    RodFromm
    Jan 23, 2024
    Users with a Plan 1 or Plan 3 license with just the default Team Member permissions can edit the project in any way they want. There are few limitations to what Plan 1 license user can do, but it's limited by the license and not the assigned permissions.

    We opened a ticket with Microsoft on this and they confirmed our findings that the assigned license privileges trump assigned permissions.

Resources