Forum Discussion
Deleted
Jan 11, 2021Project For The Web - access restrictions
Does Project For The Web have any access management capabilities? One of the users approached me with a question if it's possible to restrict write access to the project, having the majority of the t...
- Feb 07, 2021
Hello Deleted ,
Project for the web doesn't have a granular access model unfortunately. A view access license is possible at the tenant level but not project per project: https://docs.microsoft.com/en-us/project-for-the-web/office-365-user-view-access-to-project-and-roadmap
Paul
Dieter_Ly
Mar 04, 2022Copper Contributor
Is it generally possible to restrict delete of projects only to System-Admin? We must avoid, that user delete a project by accident, as it cannot be restored. We have many long-life projects..
Dieter
Dieter
Paul_Mather
Mar 04, 2022MVP
Hello Dieter_Ly ,
You can prevent users deleting a project via a custom plugin as seen here: https://techcommunity.microsoft.com/t5/project-blog/how-to-prevent-a-team-member-from-deleting-a-project-using-a/ba-p/2911074
Paul