Forum Discussion
Project For The Web - access restrictions
- Feb 07, 2021
Hello Deleted ,
Project for the web doesn't have a granular access model unfortunately. A view access license is possible at the tenant level but not project per project: https://docs.microsoft.com/en-us/project-for-the-web/office-365-user-view-access-to-project-and-roadmap
Paul
Hello Deleted ,
Project for the web doesn't have a granular access model unfortunately. A view access license is possible at the tenant level but not project per project: https://docs.microsoft.com/en-us/project-for-the-web/office-365-user-view-access-to-project-and-roadmap
Paul
Dieter
- Paul_MatherMar 04, 2022MVP
Hello Dieter_Ly ,
You can prevent users deleting a project via a custom plugin as seen here: https://techcommunity.microsoft.com/t5/project-blog/how-to-prevent-a-team-member-from-deleting-a-project-using-a/ba-p/2911074
Paul