project duration

Hi,

 

i have a file with some tasks that are seperated from each other and there is gap between tasks, i want to see what is actual duration of the tasks combined not the difference between start of first task and finish of the latest one as duration, is any way to do that ?

1 Reply

  • John-project's avatar
    John-project
    Silver Contributor

    vergilangleos

    Sure, you just need a custom Duration field with a simple formula and then sum the rollup for group and summary rows.

    John