Forum Discussion
Yolanda_jiang
Dec 19, 2023Copper Contributor
Project desktop side, when using file-sharing, the prompt is as follows
Yolanda_jiang
Dec 20, 2023Copper Contributor
Dale_HowardMVP I‘m sorry, I didn't log in to the forum to check your reply, the error screenshot in English is as follows:
I just want to share it to the sharepoint or mail, I don't know if this belongs to using project and project online, and project desktop isn't project online?
Sorry, my english is bad, and translation software is not accurate.
Thanks for your reply!
Dec 21, 2023
Yolanda --
To use the Sync with SharePoint feature to share a project, you need to have a SharePoint site already created, or you will need to create a new SharePoint site in the process. Refer to the following:
https://support.microsoft.com/en-us/office/sync-with-a-sharepoint-tasks-list-fb956d2c-723d-4d5a-b7e5-710ef82aa27a
Hope this helps.
To use the Sync with SharePoint feature to share a project, you need to have a SharePoint site already created, or you will need to create a new SharePoint site in the process. Refer to the following:
https://support.microsoft.com/en-us/office/sync-with-a-sharepoint-tasks-list-fb956d2c-723d-4d5a-b7e5-710ef82aa27a
Hope this helps.
- Yolanda_jiangDec 21, 2023Copper Contributor
Actually, I don't have this page,
when I click to sync-with-a-sharepoint, there is no response on the page, when I click twice, it will report this error:
Can you use this function normally?
Thanks.
- Dec 22, 2023Yolanda --
In that SharePoint dialog, you need to enter the URL of the SharePoint site you want to use. Is your organization actually using SharePoint? If not, all bets are off. And if yes, you should talk with your SharePoint administrator about this problem. Hope this helps.- Yolanda_jiangDec 24, 2023Copper Contributor
Dale_HowardMVP My problem now is that there is no page for me to enter the SharePoint url.
Thanks.