Project Desktop - Cost resources in Actual Cost
Hello, In Project Desktop I've assigned Cost resources to some tasks and, when tasks are marked as 100% completed, the cost resources do not appear in Actual Cost, but in Remaining Cost. Shouldn't t...
- Mar 23, 2023Alina --
When you updated the % Complete value on a task that has BOTH a Work resource AND an Expense Cost resource, Microsoft Project will only update the Actual Work for the Work resource, but it will NOT update the Actual Cost for the Expense Cost resource. This means that you will need to manually update the Actual Cost information for the Expense Cost resource. The best way to do this is to apply the Task Usage view and then display the Cost table. Enter the Actual Cost information for the Expense Cost resource assignment on the task. Hope this helps.
Mar 23, 2023
Alina --
When you updated the % Complete value on a task that has BOTH a Work resource AND an Expense Cost resource, Microsoft Project will only update the Actual Work for the Work resource, but it will NOT update the Actual Cost for the Expense Cost resource. This means that you will need to manually update the Actual Cost information for the Expense Cost resource. The best way to do this is to apply the Task Usage view and then display the Cost table. Enter the Actual Cost information for the Expense Cost resource assignment on the task. Hope this helps.
When you updated the % Complete value on a task that has BOTH a Work resource AND an Expense Cost resource, Microsoft Project will only update the Actual Work for the Work resource, but it will NOT update the Actual Cost for the Expense Cost resource. This means that you will need to manually update the Actual Cost information for the Expense Cost resource. The best way to do this is to apply the Task Usage view and then display the Cost table. Enter the Actual Cost information for the Expense Cost resource assignment on the task. Hope this helps.
Alina_Andreica
Mar 23, 2023Copper Contributor
Dale_HowardMVP Thank you very much!
Yes, I've also updated the Actual Cost in the Cost table.
But I wanted to make sure that the cost resource update is not automatic and I'm not missing any facility
Thank you again!
- Mar 24, 2023Alina -- You are more than welcome for the help, my friend!
- Alina_AndreicaMar 26, 2023Copper ContributorThank you again, my friend!