Forum Discussion
Chuck_Pollard
Jul 14, 2023Brass Contributor
Project; Bugs, Problems, and Issues
Howdy Y'all, I am generally highly adaptable and can make the most out of almost any situation. I am a long time Primavera user and I am trying extremely hard not to lose my "stuff" while making...
Jul 14, 2023
Chuck --
Hmmm. It looks like you might have Auto Calculation disabled. Click File > Options > Schedule. Scroll down to the bottom of the page and select the On option in the Calculation section of the dialog, and then click the OK button. Please let us know if this helps.
Hmmm. It looks like you might have Auto Calculation disabled. Click File > Options > Schedule. Scroll down to the bottom of the page and select the On option in the Calculation section of the dialog, and then click the OK button. Please let us know if this helps.
Chuck_Pollard
Jul 17, 2023Brass Contributor
Dale,
Thanks for the input, I checked during my initial troubleshooting. I figured it was possible one of the other folks on my team decided to fiddle with the settings even though it was unlikely, as I had it checked out most of the day.
Thanks for the input, I checked during my initial troubleshooting. I figured it was possible one of the other folks on my team decided to fiddle with the settings even though it was unlikely, as I had it checked out most of the day.