Forum Discussion

Chuck_Pollard's avatar
Chuck_Pollard
Brass Contributor
Aug 31, 2023
Solved

Project; Bugs, Problems, and Issues - Deadline Date PSA

Public Service Announcement I just found out by looking like a jackass in the middle of a meeting with lots of important people...    If you press the button for "move forward 1 day" on a mileston...
  • John-project's avatar
    Aug 31, 2023

    Chuck_Pollard 

    I guess shame on you for not understanding what happens before you're standing in front of the corporate board.

     

    The intent of the Move Tasks feature is to modify the plan as opposed to updating progress. If you instead use the Mark on Track > Update tasks feature, the deadline will stay where it is.

     

    My two cents.

    John

Resources