Forum Discussion
Molalenge
Jul 10, 2023Brass Contributor
Project Budget
If a mega project has three funding resources, $10,000,000.00: Internal resources-$5,000,000.00, donations-$2,000,000.00, and contributions-$3,000,000.00, how do you realize the amount in MS Project:...
Jul 10, 2023
Molalenge --
I would recommend that you create three Budget Cost resources named Funding - Internal, Funding - Donations, and Funding - Contributions. Apply the Task Usage view and assign these three resources to the Project Summary Task (Row 0 or Task 0). Insert the Budget Cost column and enter the appropriate Budget Cost value for each of these three resources. The Budget Cost value for the Project Summary Task will show you the total funding for the project. Hope this helps.
I would recommend that you create three Budget Cost resources named Funding - Internal, Funding - Donations, and Funding - Contributions. Apply the Task Usage view and assign these three resources to the Project Summary Task (Row 0 or Task 0). Insert the Budget Cost column and enter the appropriate Budget Cost value for each of these three resources. The Budget Cost value for the Project Summary Task will show you the total funding for the project. Hope this helps.