Forum Discussion
ingrid596
Oct 11, 2021Tin Contributor
Project Accelerator - risks, issues, changes
Hej, I wonder what needs to be changed in the configuration of the Project Accelerator so that not only the person who has registered a risk, an issue or a change can see it but at least the Projec...
- Sep 17, 2024Hello, I found the solution to this issue.
You need to configure a Hierarchy model in the Power Automate Admin Center.
In my case, I have configured the position hierarchy model and created 3 positions, Portfolio Manager, Program Manager, and Project Manager, and added one user to each position and tested. It worked, now they can see Risk/Issues/Status reports for positions lower than them.
Here is an article for more information https://learn.microsoft.com/en-us/power-platform/admin/hierarchy-security?tabs=preview
samyyounan
Sep 17, 2024Copper Contributor
Hello, I found the solution to this issue.
You need to configure a Hierarchy model in the Power Automate Admin Center.
In my case, I have configured the position hierarchy model and created 3 positions, Portfolio Manager, Program Manager, and Project Manager, and added one user to each position and tested. It worked, now they can see Risk/Issues/Status reports for positions lower than them.
Here is an article for more information https://learn.microsoft.com/en-us/power-platform/admin/hierarchy-security?tabs=preview
You need to configure a Hierarchy model in the Power Automate Admin Center.
In my case, I have configured the position hierarchy model and created 3 positions, Portfolio Manager, Program Manager, and Project Manager, and added one user to each position and tested. It worked, now they can see Risk/Issues/Status reports for positions lower than them.
Here is an article for more information https://learn.microsoft.com/en-us/power-platform/admin/hierarchy-security?tabs=preview
KatarzynaLapot
Sep 17, 2024Copper Contributor
samyyounan Thank you for sharing this. Do you know if the solution also works with custom tables?