Project 365 - how do I create a baseline?
Hi. I have Project Professional installed on my computer but I'm trying to switch over to Project 365. I don't see any option on 365 to create a baseline however. Any suggestions?
MaxBorenstein Project 365? If you meant Project for the Web, project level baselines are rolling out starting this month https://www.microsoft.com/en-us/microsoft-365/roadmap?featureid=187139
They plan to provide more detailed, task/assignment level baselines in the future.
1 Reply
- RodFrommSteel Contributor
MaxBorenstein Project 365? If you meant Project for the Web, project level baselines are rolling out starting this month https://www.microsoft.com/en-us/microsoft-365/roadmap?featureid=187139
They plan to provide more detailed, task/assignment level baselines in the future.