Forum Discussion
willard800
Jun 13, 2022Copper Contributor
Project 2019 SUMMARY TASK MISCALCULATING DURATION
Hello. My first encounter with this. One of my Summary Tasks is miscalculating the Duration for sub tasks. I have tried outdenting sub tasks, deleting "summary line", re-entering a task and indenting subs under it. Yet the Summary duration miscalculates (should be 33 dys, but shows 74 days).
would appreciated very much a solution. However, the Summary Start & Finish matches earliest and latest dates for the sub tasks. No Resources, no actuals, no % completes.
thanks
- John-projectSilver Contributor
- willard800Copper ContributorThanks for responding: Tried to paste an image, won't fill in
- willard800Copper Contributorused snipping tool copy, but won't paste here for some reason