Forum Discussion
Hans1958
Jul 21, 2023Copper Contributor
Project 2010: After filtering just for "necessary" tasks, ... the bars of the GANTT-chart have a gap
Dear all, I am using Microsoft 2010. I have 3 tasks, ... they are aaa, bbb, ccc. I have one user-defined column, called "necessary", where I declare task "bbb" not necessary. Then I filter accordi...
Hans1958
Jul 22, 2023Copper Contributor
Dear John,
Thank-you dearly for your help; it's greatly appreciated!
You said: "... However, it is only in later versions, that in addition to inactivating a task, the dependency of that deleted task is passed back to it's predecessor ...".
-> May I ask at which Version this is deloyed?
Thanks again & best regards
Hans P. ... from Germany
John-project
Jul 22, 2023Silver Contributor
Hans 1958,
I don't know which version changed how the inactivate feature works with respect to re-connecting dependencies. I have Project 2010 and Project 2019, I do not have Project 2013 or Project 2016.
John
I don't know which version changed how the inactivate feature works with respect to re-connecting dependencies. I have Project 2010 and Project 2019, I do not have Project 2013 or Project 2016.
John
- Hans1958Jul 23, 2023Copper ContributorHi John,
Thanks so much for your quick answer. It helped me! I'm very grateful for your responses! Wish you well! Keep safe! Hans ... from Germany- John-projectJul 23, 2023Silver Contributor