Forum Discussion
Project 19 is messing with the dates I insert in the task section
- Nov 28, 2022
Diony1960,
I'm glad to hear you are using auto-scheduling and saddened to hear you are "allocating dates". If I interpret that correctly, you are manually entering (allocating) dates into the Start and/or Finish fields and that is a big mistake.
The whole purpose of using auto-scheduling is to allow Project's scheduling engine to lay out the plan based on an initial start (Project Start Date), estimated duration for each task, and task relationships (Predecessors). The only time you might manually enter a task's start date is if the task independently starts sometime after the Project Start and those cases should be very rare.
I'm guessing the "strange icon" you see is the little calendar icon indicating the task has a constraint. When dates are entered manually Project sets a "start-no-earlier-than" or a "finish-no-earlier-than" constraint which circumvents Project's ability to create a dynamic schedule.
So, do NOT enter dates (other than the Project Start Date). DO enter task durations, and DO link tasks in a logical sequence. Project will calculate all dates. If the dates are unacceptable, review and modify the plan (e.g. duration and/or task dependencies) until you get what you need.
Hope this helps.
John
Diony1960,
I'm glad to hear you are using auto-scheduling and saddened to hear you are "allocating dates". If I interpret that correctly, you are manually entering (allocating) dates into the Start and/or Finish fields and that is a big mistake.
The whole purpose of using auto-scheduling is to allow Project's scheduling engine to lay out the plan based on an initial start (Project Start Date), estimated duration for each task, and task relationships (Predecessors). The only time you might manually enter a task's start date is if the task independently starts sometime after the Project Start and those cases should be very rare.
I'm guessing the "strange icon" you see is the little calendar icon indicating the task has a constraint. When dates are entered manually Project sets a "start-no-earlier-than" or a "finish-no-earlier-than" constraint which circumvents Project's ability to create a dynamic schedule.
So, do NOT enter dates (other than the Project Start Date). DO enter task durations, and DO link tasks in a logical sequence. Project will calculate all dates. If the dates are unacceptable, review and modify the plan (e.g. duration and/or task dependencies) until you get what you need.
Hope this helps.