We have users uploading (Publishing) MS Project Schedule plans online. Some files are being duplicated, and we have multiple Project plans. I have been able to edit the duplicates, but only to change...
Aug 06, 2024
rkblack1285 --
The PM who created the duplicates should open each duplicate project, and then click the name of the project. In the upper right corner of the Project sidepane, click the More Options button (the ... button) and click the Delete Plan item on the menu. Her/she will need to do this for every duplicate project. Hope this helps.
The PM who created the duplicates should open each duplicate project, and then click the name of the project. In the upper right corner of the Project sidepane, click the More Options button (the ... button) and click the Delete Plan item on the menu. Her/she will need to do this for every duplicate project. Hope this helps.
rkblack1285
Aug 06, 2024Copper Contributor
Thanks for the response, Dale. However, when I click on the (...button), there is no option for "Delete Plan" only OPen, Share, (...) Build Team.
- Aug 07, 2024rkblack1285 --
Mighty strange. How about showing us a screenshot of what you are doing? That would help us to troubleshoot the problem.- rkblack1285Aug 07, 2024Copper Contributor
- Aug 08, 2024rkblack1285 --
Well, from the screenshot you shared, it is apparent you are using Project Online. If that is the case, and if you are the Project Online application administrator, you can delete these redundant projects pretty easily. Navigate to the PWA Settings page and then click the Delete Enterprise Objects link. On the Delete Enterprise Objects page, first select the "Delete the connected SharePoint sites" checkbox, then select the checkbox for each redundant project you want to delete. BE CAREFUL deleting projects, as there is no "Undo" butto to restore a deleted project! Click the Delete button to delete the redundant projects. Hope this helps.