Progress towards a milestone
Hi, I have a bunch of tasks, which are linked to a set of key deliverables. A set of key deliverables must be met to meet a milestone. Is there a way to show the progress towards a milestone as ...
NKumar2010
May 23, 2022Brass Contributor
Hi Dale,
So you are are also suggesting I keep milestone task as a summary task, with key deliverables as it's summary task . This means the summary task shows it's progress, which essentially is a progress to achieve the milestone.
So you are are also suggesting I keep milestone task as a summary task, with key deliverables as it's summary task . This means the summary task shows it's progress, which essentially is a progress to achieve the milestone.
May 24, 2022
Refer to the screenshot below for what your project should look like. See how this project has summary tasks and a milestone for each summary task? And notice the % Complete value to the right of each summary task's Gantt bar? That is the approach I am recommending for you. Hope this helps.