Problems with export Microsoft Project Visual Reports to Excel

Hello,

I need to export a visual report from MS Project 2013 to a pivot table in Excel. When I attempt the export, MS Project displays a message stating that I need Excel 2003 or a newer version. I have a newer version, but I am unable to complete the export. What should I do?

Folow this message 

 

 

 

3 Replies

  • John-project's avatar
    John-project
    Silver Contributor

    mmacedo,

    Sorry but the link I posted in my response to Paul Ross's question is apparently no longer available. I even tried finding it on the Wayback Machine but it isn't there either. The best I can recall is that you can trick the system by installing one app first and then the other but I don't remember if it's Office first and then Project or the other way around. This link may offer some help:

    Error when opening a Visual Report in Project 2010 with Office 2013 - Microsoft 365 Apps | Microsoft Learn

    Sorry I can't be of more help. Perhaps one of my colleagues has a better memory and will jump in.

    As an aside, the Visual Reports functionality of Project has been troublesome since it was first introduced. Personally I use VBA for communicating between Project and Excel.

    John

    • mmacedo's avatar
      mmacedo
      Copper Contributor

      Olá John, 
      Minha versão do Project é de 2013 e minha versão do Office é a 365. Esse problema começou recentemente com a última atualização do Office. A solução que encontrei foi salvar uma cópia numa extensão .csv, importar os dados com Power Query e refazer os relatórios com Pivot Table. Ainda não uso totalmente o VBA. Pelo menos consegui gerar minha S Curve.

      Vou comunicar esse problema para a Microsoft Support. Vamos ver se eles vão ajudar. Acho difícil.

      Obrigado pela sua atenção. 

      Marcus

      • John-project's avatar
        John-project
        Silver Contributor

        Marcus,

        I'd say you solved your own problem. You can try Microsoft support but since Project 2013 is no longer supported, I think their response will be to upgrade.

         

        John