Forum Discussion
EduRuizAcciona
Nov 21, 2023Copper Contributor
Problema asignacion de recursos
Good morning,
I'm starting with programming in project and I have a small problem that I don't understand why project does it that way.
I have a task lasting 24 hours, conditioned by effort, with a...
EduRuizAcciona
Nov 23, 2023Copper Contributor
Good morning,
I think I already know what the project is doing to me, another thing is if I can solve it.
It is causing the four resources involved in the work to work the same hours, penalizing the fact that the work is prolonged over time.
That is to say, the work lasts 24 hours, as it assigns 4 resources, what it does is that they work 6 hours each, instead two work 8 hours and another two work 4 hours.
Now I don't know where I could change that project restriction.
Buenos dias,
Creo que ya se lo que me esta haciendo el project, otra cosa es si puedo resolverlo.
Esta haciendo que los cuatro recursos que intervienen en el trabajo, trabajen las mismas horas en el, penalizando el que el trabajo se prolongue en el tiempo.
Es decir el trabajo dura 24 horas, como le asigno 4 recursos, lo que hace es que trabajen 6 horas cada uno, en vez dos trabajen 8 horas y otros dos 4 horas.
Ahora no se donde podria cambiar esa restriccion de project
I think I already know what the project is doing to me, another thing is if I can solve it.
It is causing the four resources involved in the work to work the same hours, penalizing the fact that the work is prolonged over time.
That is to say, the work lasts 24 hours, as it assigns 4 resources, what it does is that they work 6 hours each, instead two work 8 hours and another two work 4 hours.
Now I don't know where I could change that project restriction.
Buenos dias,
Creo que ya se lo que me esta haciendo el project, otra cosa es si puedo resolverlo.
Esta haciendo que los cuatro recursos que intervienen en el trabajo, trabajen las mismas horas en el, penalizando el que el trabajo se prolongue en el tiempo.
Es decir el trabajo dura 24 horas, como le asigno 4 recursos, lo que hace es que trabajen 6 horas cada uno, en vez dos trabajen 8 horas y otros dos 4 horas.
Ahora no se donde podria cambiar esa restriccion de project
John-project
Nov 23, 2023Silver Contributor
EduRuizAcciona,
The order of resource assignments is a determining factor on how the work is distributed. For example, you will get one distribution if both "early" resources (6>2) are assigned first and then the two "late" resources (2>10) and you will get another distribution if one early resource is assigned, then a late resource, then another early resource, and so forth.
You can experiment with various assignment scenarios and each will be a little different. But, the important thing to note is that Project does NOT optimize resource assignments. Although many users assume (or wish) it did optimize assignments, the only way to obtain the resource loading you want is to first assign the resources and then manually edit the assignments.
Hope this helps.
John
The order of resource assignments is a determining factor on how the work is distributed. For example, you will get one distribution if both "early" resources (6>2) are assigned first and then the two "late" resources (2>10) and you will get another distribution if one early resource is assigned, then a late resource, then another early resource, and so forth.
You can experiment with various assignment scenarios and each will be a little different. But, the important thing to note is that Project does NOT optimize resource assignments. Although many users assume (or wish) it did optimize assignments, the only way to obtain the resource loading you want is to first assign the resources and then manually edit the assignments.
Hope this helps.
John