Forum Discussion
Problema asignacion de recursos
The exact configuration of your setup is a little confusing. Please answer these questions so we will be better able to help you.
1. What is the Project Calendar?
2. What is the Task Calendar?
3. What is the Task Type?
4. Does scheduling ignore the resource calendar?
5. What is the task Duration?
6. What is the task Work?
7. What is the Project Start Date and time?
8. What is the task Start Date and time?
John
- EduRuizAccionaNov 22, 2023Copper Contributor
First of all thank you for your helpThe project calendar is
The task calendar is 24 hours
Task type
Fixed units and conditioned by effortScheduling doesnt ignore the resource calendar
The task duration initially, before asign resources is 24 hours, and the work duration 24 hour as well. If I asign the first resource, with morning calendar (6:00 am to 14) these times stay the same. When I asign the second resource, with the same calendar, the duration reduce to 16 hour and the work remains at the same value 24 hours. When I asign the third resouce, with afternoon calendar (14 to 22) the duration increases to 16 hours and the work remains al the same value 24 hours. And with the fourth resource with afternoon calendar, the duration reduces to 14.4 hours and the work remain at 24 hours. But there are hours free of work in afternoon resource and asign hours in the morning resource the day after. I dont understand this situation
Task without resources
Task with one morning resource
Task with two morning resources
Task with two morning resouces and one afternoon resources
Task with two morning resorces and two afternoon resources
And this is the problem with the schedulingThe afternoon resource has free hours, and the morning resource work the day after
The project stardate is 25/03/2024 9:00 and the end date is calculated
Where is the problem?
Thanks for all