Forum Discussion
ZionMesilati
Apr 04, 2023Copper Contributor
predecessors as starting date for big tasks that has other task below it
Hello, I'm new on project and I want to use a task as starting point for a big task, I know that its not best practice to create this kind of connection but is there a way I can do this with out lin...
Apr 04, 2023
ZionMesilati --
If I understand correctly, you need to link approximately 200 tasks to a "big" task in your project. Assuming that those 200 tasks are predecessors to the "big" task, click the Predecessors cell for the "big" task and then click the pick list button in the Predecessors cell. In the pick list, select the checkbox for each of the 200 tasks that you want to be a predecessor for the big task. That would be the easiest way to handle this situation. If I am not understanding your question correctly, please let me know. Thanks!
If I understand correctly, you need to link approximately 200 tasks to a "big" task in your project. Assuming that those 200 tasks are predecessors to the "big" task, click the Predecessors cell for the "big" task and then click the pick list button in the Predecessors cell. In the pick list, select the checkbox for each of the 200 tasks that you want to be a predecessor for the big task. That would be the easiest way to handle this situation. If I am not understanding your question correctly, please let me know. Thanks!