Power Automate - Published Trigger - Find Who Published?
Hi, I'm trying to find the user name who published the project in Power Automate Published trigger. Is there a way to find it?
- Nov 12, 2021
Hello ramkanumuri ,
When using the Project Online Remote event receivers, that does contain the user details for who triggered that event but this hasn't been exposed in the Power Automate action.
Regarding checked out by, this is available in the REST API but only whilst the Project is actually checked out - there is no history etc. The API method is below:
{pwaUrl}/_api/ProjectServer/Projects('ProjGuid')/CheckedOutBy
Hope that helps
Paul
Paul_Mather
Nov 11, 2021MVP
ramkanumuri
Nov 11, 2021Copper Contributor
thank you @PaulMather, for your response.. Is there any other way like through user context, .. ?