Forum Discussion
Power Automate - Published Trigger - Find Who Published?
- Nov 12, 2021
Hello ramkanumuri ,
When using the Project Online Remote event receivers, that does contain the user details for who triggered that event but this hasn't been exposed in the Power Automate action.
Regarding checked out by, this is available in the REST API but only whilst the Project is actually checked out - there is no history etc. The API method is below:
{pwaUrl}/_api/ProjectServer/Projects('ProjGuid')/CheckedOutBy
Hope that helps
Paul
- ramkanumuriNov 11, 2021Copper Contributor
Paul Mather Even I was looking for 'checked out by' field in the oData/REST for the specific project but looks like this info isn't exposed. Any API that provides CheckedOutBy/Published By?
- Paul_MatherNov 12, 2021MVP
Hello ramkanumuri ,
When using the Project Online Remote event receivers, that does contain the user details for who triggered that event but this hasn't been exposed in the Power Automate action.
Regarding checked out by, this is available in the REST API but only whilst the Project is actually checked out - there is no history etc. The API method is below:
{pwaUrl}/_api/ProjectServer/Projects('ProjGuid')/CheckedOutBy
Hope that helps
Paul
- ramkanumuriNov 11, 2021Copper Contributorthank you @PaulMather, for your response.. Is there any other way like through user context, .. ?