Possibility to fill in holidays such as xmas?
Hi there
I licensed MS Project Plan 1 and I tried to figure out how I can capture holidays such as xmas. Because during some periods there is no one working and I want to include that into my project plan.
Is there any possibility for that? Or do I need Plan 3 with the ressource management module?
Thank you in advance for your help:)
Cheers
Hello dschweingruber1205 ,
Take a look at this post - that should help: https://techcommunity.microsoft.com/t5/project-blog/resource-calendars-in-project-for-the-web/ba-p/3269686
Paul
3 Replies
Hello dschweingruber1205 ,
Take a look at this post - that should help: https://techcommunity.microsoft.com/t5/project-blog/resource-calendars-in-project-for-the-web/ba-p/3269686
Paul
- dschweingruber1205Tin ContributorWell thank you! That was an easy one. Maybe I should have to dig deeper next time.
Happy Easter.
Cheers, Dani- matihCopper Contributor
I also have a similar question, in the sense that I would like to set in the project calendar all the holidays of next 2023 in order to have project taking care of those days as not available for work.
In one of the print screens which are showed in the link suggested above ( link ) I see there is the possibility to check the option "Observe business closures". I really would like to know what is the meaning of this option and where is it possibile to set the business closures. Cause I think this is exactly what I was looking for, but I was not able to find any place where to set the business closures.
Hope the question is clear somehow.
Thanks.
matih
P.S.
I'll tag also Paul_Mather 🙂 Thx.