portfolio analysis in project for the web

Dears  good day  we use project for the web for our projects .  now decided to manage the portfolio too .  Is there any possibility to have portfolio analysis in project for the web ?  As far as...
  • Paul_Mather's avatar
    Oct 16, 2024

    Hello mahnazansari ,

    This feature is only in Project Online as you have seen, it is not in Project for the web unfortunately.

    Paul