Forum Discussion
Jamesp435
Jul 25, 2022Brass Contributor
POL: Master project not inheriting formats from sub projects...
Hi Team In POL, I have a master project and 4 x sub projects linked to it. I edit all of the projects in MS Project and not in the browser. If I format a sub project, this is not reflected in the ...
- Jul 25, 2022
Sorry but that's not the way it works. Subprojects are not actually part of the master, rather, the master contains pointers to each subproject. Therefore formatting is independent.
What you can do is to create a custom formatted view and view table and store it in your Global. Then apply that pre-formatted view to each subproject and the master.
Hope this helps.
John
John-project
Jul 25, 2022Silver Contributor
Sorry but that's not the way it works. Subprojects are not actually part of the master, rather, the master contains pointers to each subproject. Therefore formatting is independent.
What you can do is to create a custom formatted view and view table and store it in your Global. Then apply that pre-formatted view to each subproject and the master.
Hope this helps.
John
- Jamesp435Jul 25, 2022Brass ContributorThanks for this John.
James- John-projectJul 25, 2022Silver ContributorJamesp435,
You're welcome and thanks for the feedback.
John