Forum Discussion

Jamesp435's avatar
Jamesp435
Brass Contributor
Jan 12, 2022
Solved

POL: Manager to view certain projects...

Hi team  I'm using POL.  I'd like a manager to view projects they are working on but not the others (similar to a PM).  Can someone give me instructions on how to do this as I'm struggling. Many th...
  • Dale_HowardMVP's avatar
    Jan 13, 2022
    James --

    Add the manager to the default Team Members group. The PMs of the relevant projects simply need to add this manager as a team member in these projects and then to publish them. By taking these steps, the manager will be able to see his/her projects in the Project Center page in PWA. Hope this helps.