POL enterprise calendar limitation...
Hi team I have about 200 resources that all have different working times. I think I read the max number of different calendars in the POL Enterprise calendar is only 20. Any thoughts how I can ge...
- Nov 02, 2021James435 --
If you are saying that among the 200 resources, there are 200 different working schedules, then you will need to edit the resource calendar for each of those resources individually. Hope this helps.