Planned vs Actual hours in MS Project Pro/PWA
We are currently in the process of migrating to PWA & Project Pro. We would like to see a view that compares what a user, by task, has planned for that period. We understand that we can se...
Ian Bruckner
Apr 03, 2024Brass Contributor
You could, however, snap "baselines" using ms project professional. There's "baseline" + "baseline1-10". Baseline (unnumbered) can show in the default "details" grid (checkbox inside "Task Usage Format"). All of those fields can be reported using oData/PowerBI.