Forum Discussion
Greema
Jul 09, 2024Copper Contributor
Planned % Complete Vs Duration Variance Vs Actual Complete
Hi, Can there be a scenario in project plan where overall the project duration is delayed, however a task actual % complete can be more that planned percentage calculated based on duration? T...
Ignacio_Martin
Jul 11, 2024Steel Contributor
Another attempt to get right on the issue, not having more data, is the situation in which the % completed of the project is lower than what could be expected, although it is progressing as scheduled and without delays to the Status Date, as shown in the picture.
This is because, as has been frequently mentioned, the formula for the % completed of a subtask summary task is:
100 x Sum of actual subtask durations / Sum of subtask durations
And the actual duration of the summary task is:
% summary task completed x summary task duration / 100
Ignacio