Planned % Complete Vs Duration Variance Vs Actual Complete
Hi, Can there be a scenario in project plan where overall the project duration is delayed, however a task actual % complete can be more that planned percentage calculated based on duration? T...
Jul 09, 2024
Greema --
Yes, this is possible, but probably only if the work in the project is "front loaded", which means that more work is planned earlier in the project, with less work planned later in the project. Hope this helps.