Planned / actual progress

Dear Community,

A more simple question where I need your comments.

What is the principle difference between the (1) Progress Line and the (2) Tracking Gantt in terms of showing the planned and actual progress .. ?

The Progress Line shows for a defined activity the gap between the current date (planned) and the progress (actual), while the Tracking Gantt shows the gap between the "planned activity" and the "actual activity".