Planification d'équipe affichage

Bonjour,

J'ai un soucis, j'aimerais afficher dans le planificateur d'équipes ma tache mais aussi les deux taches supérieur en même temps et non séparer mais je n'arrive pas gérer les affichages. J'arrive a les mettre soit l'un soit l'autre mais les 3 en même temps.

 

Avez-vous une solutions?

 

Bonne journée 

1 Reply

  • John-project's avatar
    John-project
    Silver Contributor

    DTRLTO,

    This is an English language forum so please translate before posting. Nonetheless, upon separately translating your question it appears you want to show summary level parent tasks along with each task assignment. Unfortunately the Team Planner view is very limited with regard to formatting ability and it is not possible to include associated summary level information with each task assignment.

    If I misinterpreted what you are asking please clarify and we'll try to help you.

    John