PFTW: Make or Promote Subtask Grayed Out Sporadically
I have two separate projects that were created in PFTW. One of them I can still make and promote subtasks (not grayed out) and the other project I was able to make and promote subtasks but now both o...
- Jun 06, 2025
Hello DXProgramMgr ,
On the project where this does not work - do you have any filters set:
If you do, remove the filter/s and try again.
Paul
Paul_Mather
Jun 06, 2025MVP
Hello DXProgramMgr ,
On the project where this does not work - do you have any filters set:
If you do, remove the filter/s and try again.
Paul
- ShannonN2340Aug 08, 2025Copper Contributor
Thanks a lot Paul!