PERT analysis in MS Project

Hello MS community, I am trying to understand the different version of cloud based MS Project application and it's features. Could you please advise if all the versions of Project for the web, Project Online and Project Online desktop client offers the PERT analysis to evaluate the project duration? I understood that all versions except Project for the web Plan 1 have the Critical Path functionality, but I couldn't find anything about the PERT.

Thank you.

1 Reply

  • Pavel --

    None of the tools you mention include the PERT Analysis tools. Those tools were removed in the Microsoft Project 2010 desktop software many years ago. Sorry for the bad news, but hope this helps.