P4W change start date

Hi, I try to change the start date of a task and when I select the desired date, P4W automatically sets it to another date. At first you might think that there are constraints and dependencies, but ...
  • AllDuf's avatar
    Nov 30, 2022
    Funny to say, I just found the solution. This issue was at 10 inches in the front the screen. There was a constraint with a sum task. I have to get more familiar with this new user expérience interface.