P4W - Max amount of task dependencies within a subtask list
I've run into a limitation where I am unable to select more than 8 dependencies for a single task if they are in the same subtask list. I am able to select the task in question when creating the depe...
- May 03, 2023J3B --
If you have the Microsoft Project desktop application, create the project in that tool and then import it into Project for the Web. Otherwise, I do not know of any workaround for the dependencies limitation you have encountered. Hope this helps.
May 03, 2023
J3B --
If you have the Microsoft Project desktop application, create the project in that tool and then import it into Project for the Web. Otherwise, I do not know of any workaround for the dependencies limitation you have encountered. Hope this helps.
If you have the Microsoft Project desktop application, create the project in that tool and then import it into Project for the Web. Otherwise, I do not know of any workaround for the dependencies limitation you have encountered. Hope this helps.
J3B
May 03, 2023Copper Contributor
Thanks Dale. That is what I will be doing in the meantime. Hopefully this limitation gets addressed in the future.