Forum Discussion
Myles Gallagher
Apr 20, 2018Brass Contributor
Overallocation picture only accurate with resource all projects open?
I am experimenting with project online and the desktop software as a solution for project/resource management, but I have hit some confusing problems in the program. First, let me say the auto-sched...
Trutz_Stephani
Apr 22, 2018Iron Contributor
Hi Myles,
You need to check the "Load Summary Resource Assignments" option when starting the Project client.
If you don't see it, be sure to activate the dialog:
File->Info->Manage Accounts: Configure Accounts->When Starting: "Choose an account"