Overallocation of Resource
Hi I am just doing something very simple but I am just not getting it right. I want to simulate a resource overallocation scenario and would like the red man icon to appear on the indicator column. ...
- Jan 20, 2022Kish --
Click the Resource tab to display the Resource ribbon. In the Level section of the Resource ribbon, click the Leveling Options button. In the Resource Leveling dialog, select the Manual option at the top of the dialog, and then click the OK button. Hope this helps.
Kish27
Jan 20, 2022Copper Contributor
Hi Dale
Thank you so much it cleared my issue. I spent several hours just looking what was wrong and I can only conclude some setting needs to be disable but just did not where to find. Thanks a lot
Awesome!.. This issue is now closed.
Thank you so much it cleared my issue. I spent several hours just looking what was wrong and I can only conclude some setting needs to be disable but just did not where to find. Thanks a lot
Awesome!.. This issue is now closed.