Forum Discussion
RyanEdu
Apr 04, 2023Copper Contributor
Overallocated Resources Report
Hi hoping someone can provide some clarity of on the overallocated resources report with Project online. We have a resource who as far as I can see, isn't allocated any tasks within the project b...
- Apr 04, 2023RyanEdu --
The solution is easy for this problem. In your copy of Microsoft Project, click File > Info > Manage Accounts > Configure Accounts. In the Project Web App Accounts dialog, select the "Choose an account" option in the lower left corner of the dialog, and then click the OK button. Exit Microsoft Project completely.
Re-launch Microsoft Project. In the Login dialog, DESELECT the "Load Summary Resource Assignments" checkbox and then click the OK button. From this point forward, you will no longer see the "Other projects and commitments" line in the Resource Usage view, which will allow you to focus only on overallocations in the individual project you have open.
Hope this helps.
Apr 04, 2023
RyanEdu --
The solution is easy for this problem. In your copy of Microsoft Project, click File > Info > Manage Accounts > Configure Accounts. In the Project Web App Accounts dialog, select the "Choose an account" option in the lower left corner of the dialog, and then click the OK button. Exit Microsoft Project completely.
Re-launch Microsoft Project. In the Login dialog, DESELECT the "Load Summary Resource Assignments" checkbox and then click the OK button. From this point forward, you will no longer see the "Other projects and commitments" line in the Resource Usage view, which will allow you to focus only on overallocations in the individual project you have open.
Hope this helps.
The solution is easy for this problem. In your copy of Microsoft Project, click File > Info > Manage Accounts > Configure Accounts. In the Project Web App Accounts dialog, select the "Choose an account" option in the lower left corner of the dialog, and then click the OK button. Exit Microsoft Project completely.
Re-launch Microsoft Project. In the Login dialog, DESELECT the "Load Summary Resource Assignments" checkbox and then click the OK button. From this point forward, you will no longer see the "Other projects and commitments" line in the Resource Usage view, which will allow you to focus only on overallocations in the individual project you have open.
Hope this helps.
- RyanEduApr 07, 2023Copper ContributorMany thanks Dale appreciated