Opening and Viewing Option for Two MS Project Files Simultaneously on Two Screens?
- Feb 14, 2023
You can open either 2 windows of the same file or 2 completely different files at the same time across 2 screens.
I use a triple screen set up with my laptop and 2 x 34 inch widescreen monitors, with the display setting set to extend the desktop.
To achieve this you just need to reduce the project window from full screen view to a resizable window and then drag it to fill the two screens. When you have both files open you can use the Arrange All button in the View Tab to have them side by side one on the left screen and one on the right. - Resize them as necessary to make them fit perfectly. I do this all the time and it works perfectly.
Hi MZ
Are you looking for what I have attached then follow these steps:
1) open two projects that you want to see in 2 different screen
2) then using you mouse grab the green top portion of MS project screen and drag it then you will see that ms project is coming on two screens
3) Extened on either side to cover both the screens
4) Finally go in view and click arrange all
Done!