Open MS Project file in Project Plan 3

Hello,   My company is switching over to the online Plan 3 version of Project. Some folks in our company still have MS Project on their computers. Is there anyway to open a .mpp file from my comput...
  • RodFromm's avatar
    RodFromm
    May 01, 2024

    Sara_Katz For starters, are you using MS Project Online (MSPO) or Project for the Web (PFTW)? 

    If you are using MSPO there are different versions of MSP Desktop.  One will connect to MSPO and the other will not.  Your org may need to update the version you're using and reinstall MSP on everyone's machine. 

    If you're using PFTW, I'd recommend you review the feature availability for each license type in the link below as there are differences between what a Plan 1 and Plan 3 license can do.
    Microsoft Project for the web service description - Service Descriptions | Microsoft Learn
    Here is a summary of the differences.  Also a Plan 1 license does not get an install of MSP desktop software.

     

    Feature CategoryFeaturePlan 1Plan 3
    Project, task, and time management   
     Task HistoryNoYes
        
    Collaboration and Agile   
     Task ConversationsYes1Yes1
        
    Advanced Resource and Schedule managementAdvanced DependenciesView onlyYes
     RoadmapsView onlyYes
     Critical pathNoYes
     Assignments ViewNoYes
     Create resource requests2View onlyYes
     Accept a booking proposal2View onlyYes
        
     Use Project with custom tables5515
    Power Automate Workflows and Business Process Flows6   
     Define Power Automate Business Process flows that utilize Project data including custom tables and columns.NoYes

    1 Requires a Microsoft Teams license.