online MS project number of lines limitation
Hello, I have to create a project with around 1500 lignes. I seem limited with 500 lignes when using online MS project. I'm surprised by this very low limitation. I'd like to know if there is a poss...
Paul_Mather
Jul 29, 2022MVP
Hello JPC92 ,
Project for the web does have a limit of 500 tasks per project: https://docs.microsoft.com/en-us/project-for-the-web/project-for-the-web-limits-and-boundaries#project-limitations there is no way around that until Microsoft look to support more tasks.
Project Online (Project Web App) does not have such a limit - maybe that is an option?
Paul
- JPC92Jul 29, 2022Copper Contributor
Thank you Paul
it's quite surprising because as soon as you have to plan a significant project, you're easily this limit.
I still have the opportunity to switch to local version instead of online, hopping I won't face the same constraint.
regards
Jean-Pierre
- Jul 29, 2022Jean-Pierre --
I would strongly encourage you to switch to the Microsoft Project desktop application if you can. If you continue with Project for the Web, I think you will run into many other limitations as well, none of which Microsoft Project has. Just a thought. Hope this helps.