Offline Project Plan - Missing Custom Field Values
When trying to work offline on a copy of our enterprise template, the Custom Fields are all available, but some fields are missing the values, as below. Whereas if I open the same plan...
Paul_Mather
Mar 17, 2022MVP
Hello APS1979 ,
I guess Gate is a look up table? The project client will need to be connected to the server (Project Online or Project Server) to populate that field and pick list - that is by design / a limitation.
Paul
- APS1979Mar 21, 2022Copper ContributorHi Paul, correct. I feared that was the case but hoped I'd have been proven wrong! Thanks very much for confirming, least I know the limitations now.
Cheers again.